Westmount School, Rangiora

EDR was engaged to deliver all civil, water, wastewater and utility works to support Westmount School Rangiora. The contract covered full site establishment, installation of critical infrastructure and reinstatement to Council standards.

Scope of works

The project involved a range of construction and installation tasks, including:

  • Preliminary & General - Establish site, manage traffic, locate services, complete pressure testing and sterilisation, maintain plant and materials on site and provide as-built records
  • Wastewater Rising Main - Supply, install and reinstate wastewater pipes and manholes, including directional drilling, valves, flushing points and boundary kits
  • Water Supply Pipe - Supply, install and connect water supply pipes, valves, meters and associated fittings, including directional drilling under Lehmans Road
  • Chorus Duct - Install 100mm ducting via trenching and directional drilling with full reinstatement

Project Outcome

Through efficient planning and careful coordination with stakeholders, EDR successfully delivered essential civil and utility infrastructure for Westmount School. The works were completed to specification and reinstated to a high standard, ensuring reliable long-term service connections for the facility.

Client

Canterbury Education Trust

Key EDR Staff

Harri Maguire

Contract period

June 2019

Completed Contract period

July 2019

Non-conformance at time of practical completion

Nil