Rangiora Town Hall Carpark Expansion

EDR was engaged to expand and upgrade the Rangiora Town Hall Carpark, enhancing vehicle access, pedestrian safety and overall functionality. The project included civil works, drainage, surfacing, landscaping and street furniture installation. Through careful planning and execution, EDR delivered a carpark that meets council standards, highlights historic infrastructure and improves the community experience.

Scope of works

The project involved a comprehensive range of civil and infrastructure tasks, including:

  • Preliminary & General - Site establishment, traffic management layout, erosion and sediment control setup and locating existing services
  • Excavation & Backfill - Remove existing sump, stormwater manhole and wastewater manhole, trench and install 225mm, 300mm and 100mm UPVC pipes, reconnect stormwater outlet, supply and install sumps
  • Kerb, Channel & Concrete - Remove existing kerb and channel, modify brick walls, install new kerb and channel, construct concrete slab and additional discharge channels
  • Pavement Reconstruction - Strip and remove existing asphalt, supply and place metal courses, install geotextile fabric and remake carpark pavement
  • Footpaths & Vehicle Crossings - Construct new asphalt footpath, new commercial vehicle entrance, TGSI pavers, warning studs and directional strips
  • Surfacing - Lay new asphalt surfacing (35mm DG7), raise service covers and add 700mm asphalt ramp
  • Signs, Roadmarkings & Street Furniture - Remove old road markings, install new line and ramp markings, mobility/wheelchair markings, relocate existing signs, provide mobility parking, supply and install bike racks and bench seating
  • Berm & Landscaping - Construct garden beds, supply and install 200mm x 50mm H4 treated battens, add topsoil and mulch and construct tree pits

Project Outcome

The Rangiora Town Hall Carpark Expansion delivered a fully upgraded, functional, and safe carpark for the community. EDR’s precise construction, coordinated management, and attention to detail provided an improved public space that enhances accessibility, vehicle flow and streetscape aesthetics.

Client

Waimakariri District Council

Key EDR Staff

Harri Maguire

Contract period

24 March 2025

Completed Contract period

15 August 2025

Non-conformance at time of practical completion

Nil