Woodlands Estate Subdivision Development Project

EDR was engaged to deliver a full-scale subdivision development, encompassing site preparation, installation of services, roadworks, and completion of all public and private accessways. The project provided a fully functional and safe residential environment, ready for occupancy, building and ongoing use.

Scope of works

The project involved a comprehensive range of civil construction tasks, including:

  • Earthworks - Trim and shape berms, footpaths and reserve areas, and spread screened topsoil
  • Services - Trench and backfill for common service corridors in road reserves and rights of way
  • Water Reticulation - Install new mains, laterals, valves, hydrants and connections, including testing and commissioning
  • Roading - Prepare subgrade, lay sub-base and basecourse, construct kerb and channel, and complete asphalt surfacing
  • Stormwater Drainage - Install new pipework and adjust existing manholes
  • Footpaths & Streetscapes - Build footpaths, crossings, tactile paving, road markings, signage and edge treatments
  • Right of Way (ROW) - Construct accessways with sub-base, basecourse, kerbing and asphalt surfacing
  • Practical Completion - Final inspections, testing and handover of completed works

Project Outcome

EDR successfully delivered a high-quality, fully serviced subdivision. Through precise execution and coordinated project management, the development achieved all design and safety standards, providing residents with reliable infrastructure, accessible roadways and a fully completed streetscape.

Client

Windsor Park - Waimakariri District Council

Key EDR Staff

Harri Maguire

Contract period

16 January 2023

Completed Contract period

13 February 2023

Non-conformance at time of practical completion

Nil